Speeches

Steve McCabe – 2016 Parliamentary Question to the Department for Transport

The below Parliamentary question was asked by Steve McCabe on 2016-09-14.

To ask the Secretary of State for Transport, what proportion of total spending on High Speed 2 has been on (a) wages and (b) performance bonuses.

Andrew Jones

From 2009-10 to 2015-16, the Government spent £1.4bn on the HS2 programme. The total payroll costs for HS2 Ltd permanent staff for the same period were £94.6m, out of which £113.5k was spent on performance related pay.