To ask the Secretary of State for Transport, if he will provide an estimate of the costs of redoubling the section of the North Cotswold line between (a) Charlbury to Wolvercote Junction and (b) Evesham and Norton Junction.

Stephen Hammond

The provision of a cost estimate for further redoubling of the North Cotswold line would normally be sought from Network Rail only when a business case is identified for the extra benefits this enhancement would provide. No business case has yet been identified and so a cost estimate is not being sought. Network Rail is investigating the opportunities for line speed improvements on the route to reduce journey times.