Speeches

Paul Flynn – 2015 Parliamentary Question to the Department for Energy and Climate Change

The below Parliamentary question was asked by Paul Flynn on 2015-11-10.

To ask the Secretary of State for Energy and Climate Change, pursuant to the Answer of 2 November 2015 to Question 13044, what assessment she has made of reasons for the delays in constructing reactors in China as requested in that question.

Andrea Leadsom

Whilst being a minority partner in the Taishan project, EDF expect Taishan to start generating power before the EPR at Flamanville in France, which EDF have estimated will be by the end of 2018.