Speeches

Paul Flynn – 2014 Parliamentary Question to the Department for Energy and Climate Change

The below Parliamentary question was asked by Paul Flynn on 2014-06-04.

To ask the Secretary of State for Energy and Climate Change, what information has been provided to his Department by (a) EDF Energy and (b) the Office for Nuclear Regulation on the application by EDF Energy to extend the operating life of the Dungeness B reactor.

Michael Fallon

In December 2013, the Nuclear Decommissioning Authority (NDA) received a notification from EDF Energy of the intention to extend the planned operating life of Dungeness B AGR power station (as required under the Nuclear Liabilities Funding Agreement). Information relating to this process was shared with the Department. The decision on whether in practice to extend the life of the plant will be a commercial matter for EDF Energy. This is subject to the relevant safety and security regulations.