Speeches

Lord Marlesford – 2016 Parliamentary Question to the Department for Transport

The below Parliamentary question was asked by Lord Marlesford on 2016-04-28.

To ask Her Majesty’s Government how many bat bridges over roads (1) have been completed in each of the last five years, (2) are under construction, and (3) are planned; and what is the (a) location, and (b) actual or budgeted cost of each.

Lord Ahmad of Wimbledon

One Highways England scheme has provided bat crossings as part of its construction during the last five years, and that is the A11 Fiveways to Thetford improvement scheme. Six crossings have been completed at a cost of £354,000.