Lord Jopling – 2016 Parliamentary Question to the Department for Transport
The below Parliamentary question was asked by Lord Jopling on 2016-01-27.
To ask Her Majesty’s Government, further to the Written Answer by Lord Ahmad of Wimbledon on 22 July 2015 (HL1470), whether the review of the failures that caused the cost of the recent A1 roadworks near Gamston Airport to escalate has been completed, and what conclusion and lessons have emerged from that review.
Lord Ahmad of Wimbledon
The close out of the scheme and associated financial reconciliation is pending and therefore it would be premature to draw conclusions at this time.
Landscaping for the scheme and remedial works are nearing their final stages and completion of the contract is expected at the end of March. A “lessons learned” review will be held as soon as possible in April.