Lord Berkeley – 2015 Parliamentary Question to the Department for Energy and Climate Change
The below Parliamentary question was asked by Lord Berkeley on 2015-10-22.
To ask Her Majesty’s Government which technical approvals are still outstanding in respect of the new Hinkley Point nuclear power plant.
Lord Bourne of Aberystwyth
The EPR reactor proposed for use at Hinkley Point C has successfully completed Generic Design Assessment. NNBGenCo has also received a site licence to operate the site, environmental permits and development consent. The UK’s independent regulators will continue to regulate Hinkley Point C through construction, operation and decommissioning. Specifically, once safety-related construction activities have started, the Office for Nuclear Regulation (ONR) will use the nuclear site licence to regulate construction by releasing key hold points in line with NNB GenCo’s development of the site specific safety case.