To ask the Secretary of State for Communities and Local Government, what information his Department holds on how many residential planning permissions which were granted in England in the last five years have yet to commence building work.
Gavin Barwell
As of 1 July 2016 planning permission had been granted since 1 January 2011 for 311,000 homes on sites where work had not yet started. However, latest figures show that on these sites yet to be started, 90 per cent of the dwellings are now progressing towards a start, up from 85 per cent in July 2015.
There are a range of factors which can delay the start of work on site. We are taking forward a range of proposals to help drive up delivery post permission, including changes in legislation to tackle unnecessary planning conditions and providing additional investment in infrastructure to help unlock housing sites and we expect developers and local authorities to work together to tackle problems at a local level.