Huw Merriman – 2023 Statement on the Revised Timetable for HS2

The statement made by Huw Merriman, the Minister of State at the Department for Transport, in the House of Commons on 14 March 2023.

Although we notified the House first about Thursday’s announcement, I start by apologising for the timing of the written ministerial statement, which I accept was discourteous to Members and to you, Mr Speaker.

As part of the largest capital programme ever committed, the Transport Secretary last week confirmed more than £40 billion in transport investment over the next two financial years. This will enable the opening stage of HS2 to be delivered on schedule. By 2033, passengers and communities will benefit from high-speed rail services between new stations at Old Oak Common in London and Curzon Street in Birmingham, but the House will also be aware that we face significant economic headwinds. Record inflation caused by Putin’s illegal war and ongoing global supply chain issues have ramped up construction costs, making capital projects more difficult to deliver. It means we must make responsible decisions on which parts of our capital programme we can deliver within current budgets and timeframes.

While we remain committed fully to HS2, we will need to rephase the delivery options as part of the project due to inflationary pressures and the need to spread costs. Between Birmingham and Crewe, we expect to push back construction by two years, with an aim to deliver high-speed services as soon as possible after accounting for the delay in construction. We also remain committed to delivering HS2 services to Euston, but will take time to ensure an affordable and deliverable station design, which means delivering Euston alongside the high-speed infrastructure to Manchester. While HS2 Ltd and Network Rail continue work on developing HS2 east, we are also considering the most effective way to run HS2 trains to Leeds.

The Prime Minister promised to place trust and accountability at the heart of this Government. That means strengthening connectivity across the country while managing public finances effectively. It means never shirking the tough, but necessary decisions as we deliver on the people’s priorities to halve inflation, grow the economy and reduce debt.

Iain Stewart

I am grateful to you, Mr Speaker, for granting this urgent question. As Chair of the Select Committee, we feel that there was not enough detail on a number of areas in Thursday’s statement, so I would be grateful if my hon. Friend gave further detail.

First, my hon. Friend rightly references inflationary cost pressures in construction, which are affecting all sorts of projects up and down the country, but the written ministerial statement also referenced other “increased project costs”. What are they? Is he satisfied that HS2 Ltd has a grip on its finances? Secondly, the statement said that Old Oak Common to Birmingham will be finished “as soon as possible”. What does that mean? Is there a delay to the planned opening date?

Thirdly, what is the reason for the delay to the Euston to Old Oak Common section? Is it purely down to costs or are there other reasons for a redesign? A lot of construction work is happening at Euston now, so should the redesign not have been identified earlier? Finally, when can we expect to see further detail on HS2 east, the integrated rail plan and the Leeds route options? The industry and the public require—nay, demand—certainty on this. Can we be assured that this is the last delay to the project?

Huw Merriman

I thank my hon. Friend the Chair of the Transport Committee for his questions. I will provide some answers, but there will no doubt be further detail to discuss as we go through the session.

On my hon. Friend’s question about the increased project costs, they chiefly relate to the opening section of the line in phase 1, which is the part that is under construction at the moment. We are spending about £600 million a month on phase 1 construction, which is at its peak. He rightly talks about inflation; the Office for National Statistics shows that construction inflation is running at about 15%, which is why we have an issue with costs. He is right to say, however, that we need to bear down on costs. Yesterday, I met the chief executive of HS2 Ltd. I am delighted with the appointment of the chairman, Sir Jon Thompson, who has a background in finance. Certainly, it is within HS2’s requirements to ensure that, where we have inflationary pressures, it fills the gap by bearing down on costs.

My hon. Friend asked what finishing Old Oak Common to Curzon Street “as soon as possible” means. As I stated in my opening remarks, we expect that, by 2033, passengers and communities will benefit from high-speed rail services between those two stations. He asked about the reason for the Euston delay. Euston was always scheduled for delivery after the opening of phase 1, which is why we are prioritising Old Oak Common. We will not proceed with construction at Euston in the next two years, due to affordability and profiling issues, but we will use that time to work with partners to ensure an affordable and deliverable design.

My hon. Friend asks for detail on HS2 east, the integrated rail plan and the Leeds route study. I will be writing to him on the back of the integrated rail plan report this month and further information will be tabled in the six-monthly HS2 report, which is due in May. On the Leeds route strategy, it has been cleared by the Department and we expect it to be published soon.

My hon. Friend is right to say that the industry needs certainty, and I believe he asked whether we can be certain that this is the last change to the project. Although the pandemic and Putin’s illegal invasion of Russia were not anticipated, we expect these HS2 plans to be the plans that deliver it from London to Manchester.