To ask the Secretary of State for Defence, what the costs of infrastructure improvements at RAF Waddington were in each year from 2010-11 to 2014-15.
Mark Lancaster
The costs of infrastructure improvements at RAF Waddington in each financial year from 2010-11 to 2014-15 are shown in the following table:
Financial Year |
Grand Total |
2010-11 |
£1,494,929.99 |
2011-12 |
£2,794,486.46 |
2012-13 |
£2,503,485.61 |
2013-14 |
£1,044,565.26 |
2014-15 |
£18,857,704.44 |
Grand Total |
£26,695,171.76 |
The significant increase in Financial Year 2014-15 is due to the Waddington boiler replacement work, the upgrade of Single Living Accommodation, and the start of the construction phases of the reconstruction and resurfacing of the runway and hangar refurbishments.