To ask the Secretary of State for Defence, what the total additional cost was of the net 52-month deferment of the final stage of the Core Production Capability Project.

Mr Philip Dunne

As stated in the National Audit Office (NAO) Major Projects Report (MPR) 2015, the Core Production Capability project was deferred for 52 months due to the decision to refuel HMS Vanguard and keep the option open to refuel HMS Victorious. As a result of this new requirement that was unforeseen, an additional £196 million was approved for this project of which £17.6 million represents the cost of deferment.