To ask the Secretary of State for Transport, when he expects the timetable for construction of High Speed 2 Phase One in Chesham and Amersham constituency to be published.

Mr Robert Goodwill

Finalising the construction timetable for works in this area will be the responsibility of the Main Works Contractor when they are appointed following Royal Assent. An indicative construction programme for Chesham and Amersham is set out in Volume 2 of the Environmental Statement (ES) – CFA reports 8-9. This indicates advanced works commencing in the first quarter of 2017, with civil engineering works commencing in the fourth quarter of 2017.