To ask the Secretary of State for Health, with reference to his Answer of 9 May 2016 to Question 35866, what the capital spend by (a) the Health Protection Agency on its National Incident Coordination Centre in 2011 at Buckingham Palace Gate and (b) Public Health England on its National Emergency Operations Centre in Wellington House was in 2015.

Jane Ellison

Public Health England was established in 2013. Therefore the Department has not been able to specifically identify the historical costs of creating the National Incident Coordination Centre (NICC) in 2011.

The works to install the NICC was part of a wider refit of 5th Floor North in Wellington House. The project cost for this refit was £43,000; the cost of installing the NICC cannot be specifically identified.