The below Parliamentary question was asked by Lord Berkeley on 2016-03-16.
To ask Her Majesty’s Government what is their latest estimate of (1) the number of HS2 trains of each size required for HS2 Phase 1 and HS2 Phase 2, and (2) the total cost (a) of each type of train, and (b) for each phase.
Lord Ahmad of Wimbledon
The Functional Response annexed to the Development Agreement outlines what HS2 Ltd will deliver to satisfy the Sponsor’s Requirements, including capacity requirements for both phases of the new railway. HS2 Ltd are in the process of completing their Rolling Stock Strategy which will contain greater detail on the fleet sizes expected to be procured.
As part of the Spending Round announced in November 2015, the rolling stock funding envelope has been integrated with the relevant Phase specific infrastructure funding envelope as shown below.
Phase One |
27.2 |
Phase Two |
28.5 |
Programme Total |
55.7 |
Note. The above table shows information in £Billion at 2015 prices.