Cheryl Gillan – 2016 Parliamentary Question to the Department for Transport
The below Parliamentary question was asked by Cheryl Gillan on 2016-01-19.
To ask the Secretary of State for Transport, what his most recent estimate is of the cost of tunnel boring for the High Speed 2 Chiltern tunnel.
Mr Robert Goodwill
The estimated cost of the Chiltern tunnel, as extended via Additional Provision 4, is £940m (based on Q2 2011 Prices). This figure, which includes the costs relating to tunnel boring and the construction of the tunnel portals and vent shafts, excludes risk and contingency.